Victorville, Calif., Examines Power Plant Plans for 'Irrelevant' Details.(Knight Ridder/Tribune Business News)

Knight Ridder/Tribune Business News, March, 2000 by Materna, Jessica

Mar. 6--A plan to break ground in April on a $350 million power plant at Southern California Logistics Airport is losing some steam as a state agency mulls project details deemed "irrelevant" by both developers and city officials.

The Newport Beach-based developer of the 750-megawatt High Desert Power Project said the California Energy Commission Energy Resources, Conservation and Development Hearing Committee's Feb. 18 request for more information on the project's well system is "unnecessary," and may delay construction.

Victorville officials agreed, saying the city doesn't want to risk losing months of anticipated tax revenue to delays. The power plant is expected to generate tax revenue of $264,000 a month once it starts operations in spring of...

Premium Content Partnership | HighBeam Research provides an in-depth online archive library of reference works. HighBeam Research

 

BNET TalkbackShare your ideas and expertise on this topic

Please add your comment:

  1. You are currently: a Guest |
  2.  

Basic HTML tags that work in comments are: bold (<b></b>), italic (<i></i>), underline (<u></u>), and hyperlink (<a href></a)

advertisement
Click Here
advertisement
  • Click Here
  • Click Here
  • Click Here
advertisement