Transportation Industry
Construction of intermodal facility at Stockton, Calif
Railway Track and Structures, Sept, 2003 by Eugene D. Schubel
What happens when a company does careful planning and works closely with local agencies to construct a new world-class facility?
The outcome is Burlington Northern and Santa Fe's intermodal facility, near Stockton, Calif., which recently received a 2002 Regional Excellence Award for innovative use of time treatment for subgrade.
Also in 2002, BNSF was recognized by area agencies as the premier pollution preventer for its efforts. The County of San Joaquin gave BNSF the award, citing improvements in the environmental categories of land, water and air. Besides providing additional wildlife habitat, storm water runoff became controlled traffic congestion and the number of trucks on area highways were reduced.
John Fleming, resident engineer accepted the award on behalf of BNSF. "The project faced many challenges during construction, and during that time the BNSF construction team established great working relationship with all agencies concerned. The project was completed ahead of schedule, under budget and more than 300,000 man-hours worked without a loss-time injury."
The facility, which opened April 2001, has grown in volume with additional parking added at the end of 2002. The initial construction created two 7,70-0foot-long strip tracks, three storage tracks and 900 parking stalls. The design allows for future parking, strip and storage tracks. The facility can handle minimum of 300,000 lifts per year DMJM Harris, Long Beach, Calif., was the designer and construction manager for the project. Kleinfelder, Stockton, Calif., provided the geotechnical support and designed the subgrade.
The civil work was performed by Granite Construction, Stockton, Calif., and BNSF track forces constructed all trackage. The real challenge involved stabilization of native soils before paving materials were applied. A lime-stabilized section 31-inches thick was constructed under the concrete paved loading and unloading areas. The entire lime treating process made it one of the largest lime stabilization projects in the United States, totaling 440,000 cubic yards of treated soil, covering 220 acres.
Drainage features included three retention basins, totaling 46 acres and one million cubic yards of excavation, seven miles of subdrains and six miles of storm drain pipe. The contractor used some creative thinking to overcome environmental and material supply obstacles. One example, the concrete storm drain was not readily available, so a cast-in place approach was used to prevent schedule delays.
Another challenge to timely completion was Weber Slough, which cuts diagonally across the site. This waterway was identified as a habitat for the giant garter snake, a threatened species. From October through April, work could not be performed in this area. The mitigation for the waterway, other wetland impacts and several animal species will be discussed later.
Another creative approach used by the contractor to expedite the concrete box construction in the slough, was to use of rolling steel forms. The bottom slab was prepared first, then movable forms used to construct the walls and top of the boxes in segments. Since the concrete box section consisted of four barrels with a total width of 53 feet and a depth of seven feet, six inches, this structure could not have been easily pre-cast and placed.
The concrete paving for the loading and unloading area was designed to accommodate use of a reach stacker. Although this type of equipment is no currently used, the flexibility to use it in the future was desired. Since expansive clays were the predominate soil type on the site, the deep lime section, previously mentioned, allowed the concrete pavement to be only 13 inches thick. The over all support structure was economically designed and with actual strengths being exceeded, the durability of the pavement section was enhanced.
The paving machine used on the project was only one of four that existed a that time. It was totally-computerized capable of paving a 40-foot-wide section and had special features, such as an automatic dowel bar inserter. This saved the manual labor that is normally used for this step. An onsite batch plant was setup to produce nearly 66,000 cubic yards of concrete that was required.
The mitigation for wetlands and loss of habitat for some animal species resulted in construction of a wetland preserve, which covers 56 acres. Four side pools were created by diverting water from the mitigation channels via diversion channels. A native planting plan was implemented within the preserve along with a temporary drip irrigation system.
Another successful part of the construction was encouraging the contractor to make value-engineering recommendations through the CRIPS, or Cost Reduction Incentive Programs. The savings were shared between BNSF and the contractor Two such recommendations involved changes in the strip track drainage system and the jointing of the concrete pavement.
Gene Schubel, director engineering services, BNSF, was the project manage for the project. "As with any project some mistakes were made and lesson learned to apply to future projects."
- 5 Rules for Immediate Annuities
- Death in the Family: 12 Things to Do Now
- Dumbest Things You Do With Your Money
- 6 Online Networking Mistakes to Avoid
- 401(k) Mistakes to Avoid
- 5 Economic Scenarios to Keep You Up at Night
- The Real ‘Best Places to Retire’
- Best Credit Cards for You
- 12 Tough Questions to Ask Your Parents
- The Real ‘Best Colleges’
- Home Buyer Tax Credit: How to Cash In
- Why You Shouldn't Bash Cash
- 8 Phony 'Bargains' and Better Alternatives
- Danger: 3 Debit Card Scams to Avoid
- 6 Myths About Gas Mileage
- 29 Fees We Hate Most
- Quick and Easy Ways to Boost Returns
- Best Stocks to Buy Now
- Lower Your Taxes: 10 Moves to Make Now
- New Jobs: 8 Lessons from Real-Life Career Switchers
- The New Job Market: Who Wins and Who Loses?
- Health Care Reform's Public Option: Everything You Need to Know
- Volunteer Work When Unemployed: Should You Work for Free?
- Whose Recovery Is This?
- Long-Term-Care Insurance: 4 Biggest Risks to Avoid
Content provided in partnership with
Most Recent Business Articles
- Multiple criteria evaluation and optimization of transportation systems
- Multi-criteria analysis procedure for sustainable mobility evaluation in urban areas
- A two-leveled multi-objective symbiotic evolutionary algorithm for the hub and spoke location problem
- Multi-criteria analysis for evaluating the impacts of intelligent speed adaptation
- The development of Taiwan arterial traffic-adaptive signal control system and its field test: a Taiwan experience
Most Recent Business Publications
Most Popular Business Articles
- 7 tips for effective listening: productive listening does not occur naturally. It requires hard work and practice - Back To Basics - effective listening is a crucial skill for internal auditors
- FAS 109: a primer for non-accountants - Financial Accounting Standards Board's "Statement 109: Accounting for Income Taxes"
- LIFO vs. FIFO: a return to the basics
- Design a commission plan that drives sales - Sales Commissions
- Using object-oriented analysis and design over traditional structured analysis and design


