Equipment startup checklist—AHU

Engineered Systems, Jan, 2005 by Amanda Mckew

Equipment type: AHU
Equipment designation: AHU-1
Bar code designation: ###

ELECTRICAL INSPECTION                                          YES   NO

* Electrical completed and disconnect installed per code
compliance.                                                     []   []

* Starter and wire sized per contract documents.                []   []

* Motor "bumped" to verity rotation.                            []   []

* Terminations and panel circuit labeled.                       []   []

* Voltage and motor amps (per phase) documented.                []   []

ELECTRICAL INSTALLATION (PER CONTRACT DRAWINGS
AND SPECIFICATION)                                             YES   NO

* Ductwork complete.                                            []   []

* Piping complete.                                              []   []

* Vibration isolation complete.                                 []   []

* Seismic restraints complete.                                  []   []

* Manufacturers' O&M available.                                 []   []

* Manufacturers' startup sheets attached with
this checklist.                                                 []   []

* Warranty certificate available.                               []   []

DISTRIBUTION (TO AND FROM EQUIPMENT)                           YES   NO

* Duckwork pressure tested per contract documents.              []   []

* Piping pressure tested per contract documents.                []   []

* TAB report (and field notes) attached with this checklist.    []   []

Identification per contract documents.                          []   []

AUTOMATIC CONTROLS                                             YES   NO

* Temperature controls complete.                                []   []

* Control points confirmed.                                     []   []

* Electrical system interlocks complete.                        []   []

* Fire alarm interface complete.                                []   []

* Security interface complete.                                  []   []

TRICKS OF THE TRADE

* Attach equipment schedule and design criteria to checklist.

* Attach sequence of operation to checklist.

* Attach associated contract detail drawing to checklist.

* Complete missing equipment data sheet for CMMS when providing initial PM workorder requirement.

* Have a system flow diagram when starting up the equipment with estimated flows, pressure, and pressure drops noted on diagram.

* Refer to equipment manufacturers' literature for additional data and requirements.

* This checklist should be completed prior to system commissioning process.

REFERENCE

* 2004 ASHRAE Handbook--Systems & Equipment.

* 2003 ASHRAE Handbook--Applications, Chapter 3 (restaurants/cafeterias).

DESIGN REVIEW / TRICKS OF THE TRADE

* Confirm there is safe access to the equipment.

* Confirm there will not be short-circuiting of exhaust air into air intakes and/or other building openings.

* Spot-check cooling capacity by dividing square feet by tons-cooling for sq ft/ton.

* Spot-check total fan static (and velocity pressure) for excessive/inadequate pressure drop.

* Attach equipment schedule and design criteria to checklist.

* Attach sequence of operation to checklist.

* Attach associated contract detail drawing to checklist.

NOTE

* Refer to equipment manufacturers' literature for additional data and requirements.

COPYRIGHT 2005 BNP Media
COPYRIGHT 2008 Gale, Cengage Learning

 

BNET TalkbackShare your ideas and expertise on this topic

Please add your comment:

  1. You are currently: a Guest |
  2.  

Basic HTML tags that work in comments are: bold (<b></b>), italic (<i></i>), underline (<u></u>), and hyperlink (<a href></a)

advertisement
CXO UnpluggedSmart Business interviews on BNET

See and hear how senior level executives across the Asia Pacific are developing smart business ideas across a variety of sectors. The focus is on the future, and on how businesses need to evolve.

advertisement
  • Click Here
  • Click Here
  • Click Here
advertisement

Content provided in partnership with Thompson Gale