Design review / design build: MDF room packaged HVAC unit/system

Engineered Systems, August, 2007 by Amanda McKew

Job number:
Area served: Main distribution frame (MDF) room
Equipment type: Packaged HVAC unit
Equipment Designation: CACU-1
Barcode designation: 11111
Equipment location: In occupied space

DESIGN REVIEW                                              [Y]   [N]

* Verify adequate equipment room ventilation.              ()    ()
* Spot-check air quantity by determining cfm/sq ft.        ()    ()
* Spot-check heating capacity by determining Btuh/sq ft.   ()    ()
* Spot-check cooling capacity by dividing total cfm by     ()    ()
  400 = tons and OA cfm by 300 for dehumidification
  tons.
* If underfloor air system is utilized, confirm there      ()    ()
  are enough perforated tiles in the floor for adequate
  airflow.
* Create system flow diagram to assess static pressure     ()    ()
  sequence of operation, condenser water, and/or chilled
  water pressure drops.
* Spot-check fan total static pressure by comparing with   ()    ()
  fan total static pressure of inch based on dirty
  filters (prefilter + after filter + final filter).
* Review if unit is chilled water, DX condenser water      ()    ()
  with DX, or dry cooler-based.
* Confirm coils are piped correctly per manufacturer's     ()    ()
  piping requirements.
* Review specifications to confirm space humidity/         ()    ()
  temperature setpoints are specified and within high/
  low alarm limits.
* Review specifications and confirm alarm delay duration   ()    ()
  is specified 0 to 255 seconds.
* Review specifications to determine if unit or floor      ()    ()
  leak detection was specified.
* Review control drawings and specifications to            ()    ()
  determine if unit will be tied to an AC or universal
  panel.
* Review control drawings and specifications to            ()    ()
  determine if unit will operate as a standalone unit,
  on a network or BAS/BMS.

ELECTRICAL INSPECTION/REQUIREMENTS                         [Y]   [N]

* What are the new electrical requirements for the new     ()    ()
  CACU?
* Is there adequate electrical power to meet new           ()    ()
  electrical load from CACU?
* Will emergency power be a requirement for the new        ()    ()
  CACU?
* Are electrical connections tight and secure?             ()    ()
* Have the fuses and wire sizes been checked and           ()    ()
  verified?
* What electrical system components (existing conduits,    ()    ()
  light fixtures, panels, etc.) will require removal,
  reinstallation, and/or relocation?
* Are there existing electrical code issues that should    ()    ()
  be address at this time?

HVAC INSPECTION/REQUIREMENTS                               [Y]   [N]

* Has selection of CACU been approved and signed off by    ()    ()
  owner?
* Have cold/hot water management system been completed     ()    ()
  in an automatic control-functional performance action
  /reaction matrix?
* Have gpm-pressure drop-velocity been noted on            ()    ()
  distribution points of the water piping flow diagrams?
* Have pump curves been assessed for optimum               ()    ()
  performance?
* Verify that water piping is complete and correct         ()    ()
* Can the CACU be installed with access for maintenance?   ()    ()
* Has consideration been given to future expansion of
  system?
* Has system flushing been determined in scope of work?    ()    ()
* Has condensate drain piping be addressed?                ()    ()
* Has consideration be given to the manufacturers'         ()    ()
  recommended clearance around equipment for service?
* Has hot corridor / cold corridor been considered?        ()    ()

PLUMBING REQUIREMENTS                                      [Y]   [N]

* Have floor drains been coordinated?                      ()    ()
* Have backflow preventors been considered?                ()    ()
* Has a water filter been considered for city water to     ()    ()
  humidifier?

GENERAL CONSIDERATIONS/REQUIREMENTS                        [Y]   [N]

* What are the necessary installation permitting and       ()    ()
  operation permitting requirements?
* Will record drawings be submitted electronically along   ()    ()
  with one paper copy?
* Will there be an extended warranty on the equipment?     ()    ()
* Will there be a service contract submitted for the new   ()    ()
  CACU?
* Will CACU O&M website be included along with             ()    ()
  electronic copy or O&M manual and two paper copies of
  manual?

If you have any comments, suggestions, or questions regarding this designer checklist, contact Amanda McKew at amckew@rdkengineers.com.

This column is meant to provide some basic guidelines for good design. Always consult all necessary codes and resources relevant to each particular project.

COPYRIGHT 2007 BNP Media
COPYRIGHT 2008 Gale, Cengage Learning
 

BNET TalkbackShare your ideas and expertise on this topic

The following tags are supported in BNET comments:
<b></b> <i></i> <u></u> <pre></pre>

Leave a Reply

  1. You are currently a guest | Login?
advertisement
CIO SessionsVision Series on ZDNet

See and hear what CIOs the world over thinks about the business of technology and how it's changing the way we live and work.

Go
advertisement
  • Click Here
  • Click Here
advertisement

Content provided in partnership with Thompson Gale