Newport Chemical Agent Disposal facility project management team: leveraging fidelity of performance-based metric tools for project management - Performance Measurement

Program Manager, Jan-Feb, 2003 by Scott S. Haraburda

The Chemical Stockpile Disposal Program (CSDP) is a U.S. Army program implemented to achieve destruction of the nations stockpile of chemical warfare agents by April 29, 2007. In support of that program the Newport Chemical Agent Disposal Facility (NECDF) is being designed to neutralize the chemical nerve agent VX that is stockpiled in bulk quantities at the Newport Chemical Depot (NECD), Newport, Ind. This low-temperature and low-pressure neutralization process provides an alternative to the baseline incineration technology previously selected by the Army for chemical warfare agent disposal.

A Brief History

During the first couple of years, the project manager for the NECDF project had regularly received massive amounts of project-related data from the project management team. Additionally, the team would provide data and expect the project manager to: 1) interpret the information, 2) identify the major issues and concerns, and 3) provide direction to solve the issues. On a project of this magnitude, their expectations translated into a very time-consuming task for the project manager and a distinct distraction from managing the project's more critical areas.

To improve communications between the project manager and members of the project management team, an improved method for applying performance metrics on the project was developed. This involved the following:

* Selecting key areas on the project to be assessed periodically using the improved method. As an example, the following nine project areas were selected: construction, contracting, cost, design, environmental, operations, safety, scheduling, and staffing.

* Appointing individuals, such as subject matter experts, to monitor and maintain the metrics for the key areas selected.

* Developing an effective performance metric for each key area.

* Creating a four-block page that summarizes the important information for each area.

* Establishing a single dashboard page that visually highlights the overall status of the project.

Performance-Based Metrics

The basic functions of project management involve planning, organizing, controlling, and directing human efforts. Managers should use performance-based metrics as a tool to assist the project manager in these basic functions.

Using just any metrics may result in a situation creating the illusion that managers are being effective. In essence, using the correct metrics is very important. To ensure that the correct metrics are being used, managers need to understand the type of metric being used and the source of the data used in the metric.

First, the type of metric used is important so that managers can use it to influence the project, as required, to ensure that necessary tasks are accomplished. To facilitate their efforts, managers could look at a process in terms of its three elements: Input, Work, and Results. These elements can be portrayed as functions that depict the interface between the three groups of people within the project: suppliers, the customer, and the project manager/ leader (Figure 1).

The type of metric selected should fall within the interfaces between the three groups of people, as they fit into the three elements of the project process.

Inputs

Resources. This refers to the amount and quality of the items used by the project, such as staffing, materials, equipment, tools, utilities, etc.

Controls. This refers to the methods and means by which the project manager influences the way work is done. An example of this would include operating procedures, standards, and schedules.

Work

Process. This refers to the way work is done for the project. This includes the efficiency of the work and the compliance with the project's operating procedures/standards.

Output. This refers to the amount, quality, and timeliness of the products and services provided by the project. This is typically supplied to the customer of the project.

Results

Feedback. This refers to the perception of the customers--how they view the project as determined by the demands they place upon the products (output). The use of surveys (proactive) could be used in addition to customer complaints (reactive).

Outcome. This refers to the customers benefits from the products and services resulting from the project.

Understanding the Source

Finally, the project manager should understand the source of the data for the selected metric. To be effective, the metric should be:

Accurate. For the data to be accurate, they must be valid and reliable. Valid data refer to data that can be directly related to factors being measured. One aspect of valid data being collected is that of causality The manager must take special care to ensure that the data being collected caused the effect to occur. Reliable data refer to data that would be consistent regardless of the data collection technique. An effort should be made to eliminate or minimize errors in data collection due to rater bias, data collection administration, and wording.

Relevant. For the data to be relevant, they must be credible and important. Credible data refer to data that will be believable by the people making the decisions, such as managers. Managers should ensure there is a plan or baseline from which to compare, which should include the goals. Important data refer to data that address the important items associated with the factors being measured. For example, managers should not use metrics on trivial items just because they are easy to measure such as the number of hours that groups of people worked. In this case, a better measurement would be the output of the work performed by these groups.

 

BNET TalkbackShare your ideas and expertise on this topic

Please add your comment:

  1. You are currently: a Guest |
  2.  

Basic HTML tags that work in comments are: bold (<b></b>), italic (<i></i>), underline (<u></u>), and hyperlink (<a href></a)

advertisement
Click Here
CXO UnpluggedSmart Business interviews on BNET

See and hear how senior level executives across the Asia Pacific are developing smart business ideas across a variety of sectors. The focus is on the future, and on how businesses need to evolve.

advertisement
  • Click Here
  • Click Here
  • Click Here
advertisement
Click Here

Content provided in partnership with Thompson Gale