Waiting for privatisation: Saudi Arabia's electricity generation and distribution programmes offer tremendous scope for investment but only after the promised privatisation measures have been put in place
Middle East, The, Jan, 2005 by Neil Ford
WHEN SAUDI ARABIA'S SUPREME ECONOMIC Council ordered the formation of the Electricity Regulatory Authority (ERA) at the end of November 2001, it seemed as if competition in the Saudi electricity sector could not be far behind. Why set up a regulator without a genuine market to regulate? Yet although the government remains committed to unbundling the Saudi Electric Company (SEC), it appears loath to loosen its control of the industry.
While the government has not made an express commitment towards the privatisation of the power sector, it has certainly moved in that direction. Greater private sector participation is being encouraged, while SEC is to be divided into generation, transmission and distribution components. It remains to be seen how much competition this will engender and how many separate business units will be formed. The creation of the ERA seemed to point towards a more competitive market, but its responsibilities at present appear confined to integrating independent power producers (IPPs) with the rest of the sector.
With or without sector reform, new generating plants are a priority because of annual growth in demand in excess of 5% and the inadequacy of existing capacity. Continued population growth and rising per capita electricity consumption should see demand continue to rise just as quickly for the foreseeable future. The Saudi electrification rate stands at just over 80% and SEC is unlikely to complete its rural electrification programme until the end of the decade. However, connecting new consumers should help to maintain levels of demand growth.
According to the Ministry of Industry and Electricity, 20GW of new capacity is required over the period 2003-2019 and given the length of time required to develop new plants, it is vital that a long term strategy for achieving this goal is put into place as soon as possible. Although national generating capacity currently stands at just 26.6GW, Saudi Arabia's plans for industrialisation and its plentiful gas reserves mean the 20 GW target is not overly ambitious. It is likely that the lion's share of new capacity will be provided by gas fired plants. Apart from the ease of using domestic reserves, the durability of high oil prices and the government's desire to maximise oil exports should rule out new oil fired plants, even though new technology makes them a cleaner option.
The government hopes private sector developers can provide most of the new generating capacity required; although it is still unclear how privately funded plants will fit in to the rest of the sector. Towards the end of 2003, SEC announced plans for $4.5bn of new infrastructural investment. Some of the money is being put into new interconnectors in order to ease the transmission of electricity around the country, creating a more comprehensive national power grid. However, as Table 1 outlines, seven new generating plants are also to be built, providing over 14GW of new capacity.
SEC has only been in existence since 2000, when the government merged the country's various power companies, all of which are believed to have been in debt because of mandatory low tariffs. The sector is still unofficially subsidised thanks to artificially low tariffs that are set by the government and although it is intended that SEC should be financially viable, this seems an unattainable aim at the current time without government support.
Major private sector companies are already active in the sector. For example, CMS Energy is constructing a 250MW cogeneration plant for the Saudi Petrochemical Company, while Bechtel and Mitsubishi are developing the 2,400MW Ghazlan II plant at a cost of $1.7bn. The first turbines have already been brought on stream and the plant is scheduled for completion later this year. Further plants are likely to be built in build-own-transfer (BOT) and build-own-operate (BOO) contracts and are likely to be planned by the government and SEC rather than by private companies identifying good opportunities for IPPs. Despite the lack of sector reform, foreign companies benefit from the absence of customs duties and a 10 year tax holiday when investing in power sector projects.
The government is also looking to independent water and power producers (IWPPs) to provide a large proportion of new generating capacity. New technology has cut production costs for both electricity and drinking water and so IWPPs offer a great deal of additional benefit in such a water-poor country as Saudi Arabia. SEC has drawn up plans for four new IWPPs, each of which was originally included in the now abandoned Gas Initiative. Each IWPP is expected to cost over $1bn to develop, while the four should provide combined generating capacity of 5,000MW.
The government hopes to offer 60% stakes in each project to private companies. However, under the current regulatory environment, investors may require guarantees on tariff levels and so are expected to sign long term sales agreements with SEC and the Saline Water Conversion Corporation (SWCC). The latter, which has been listed for privatisation, would like to develop a raft of new desalination plants but these remain on the drawing board at present.
- 5 Rules for Immediate Annuities
- Death in the Family: 12 Things to Do Now
- Dumbest Things You Do With Your Money
- 6 Online Networking Mistakes to Avoid
- 401(k) Mistakes to Avoid
- 5 Economic Scenarios to Keep You Up at Night
- The Real ‘Best Places to Retire’
- Best Credit Cards for You
- 12 Tough Questions to Ask Your Parents
- The Real ‘Best Colleges’
- Home Buyer Tax Credit: How to Cash In
- Why You Shouldn't Bash Cash
- 8 Phony 'Bargains' and Better Alternatives
- Danger: 3 Debit Card Scams to Avoid
- 6 Myths About Gas Mileage
- 29 Fees We Hate Most
- Quick and Easy Ways to Boost Returns
- Best Stocks to Buy Now
- Lower Your Taxes: 10 Moves to Make Now
- New Jobs: 8 Lessons from Real-Life Career Switchers
- The New Job Market: Who Wins and Who Loses?
- Health Care Reform's Public Option: Everything You Need to Know
- Volunteer Work When Unemployed: Should You Work for Free?
- Whose Recovery Is This?
- Long-Term-Care Insurance: 4 Biggest Risks to Avoid
Content provided in partnership with
Most Recent Business Articles
- CORRECTION FROM SOURCE/Media Advisory: Fallen Canadian Soldiers and Journalist Return Home
- Fox Networks Group and Bright House Networks Strike Comprehensive Deal to Distribute Fox Broadcast Stations, National Cable and Regional Sports Networks
- Fox Networks Group and Time Warner Cable Strike Comprehensive Deal to Distribute Fox Broadcast Stations, National Cable and Regional Sports Networks
- Houston Radio D.J. Kevin Kline Completes 500-Mile, 13-Day Ultramarathon Across Texas for Kids with Cancer
- Seaspan Corporation Provides Information on the CSCL Hamburg
Most Recent Business Publications
Most Popular Business Articles
- 7 tips for effective listening: productive listening does not occur naturally. It requires hard work and practice - Back To Basics - effective listening is a crucial skill for internal auditors
- FAS 109: a primer for non-accountants - Financial Accounting Standards Board's "Statement 109: Accounting for Income Taxes"
- LIFO vs. FIFO: a return to the basics
- Using object-oriented analysis and design over traditional structured analysis and design
- Design a commission plan that drives sales - Sales Commissions