Transportation Industry
Industry: Email Alert RSS FeedBridge temporary works research program
Public Roads, Sept, 1991 by Sheila Rimal Duwadi
Bridge Temporary Works Research Program
Introduction
On August 31, 1989, the Route 198 bridge over the Baltimore-Washington Parkway collapsed, injuring nine workmen and five commuters--one critically--when 400 tons (363 Mg) of steel and concrete fell on the parkway without warning (figure 1). The collapse was subsequently and independently investigated by the Federal Highway Administration's (FHWA's) Federal Lands Division and a private consultant. Upon completion of the investigation, the FHWA Administrator established an impartial board of review to study and evaluate all aspects of the two investigations, determine the basic cause for the failure, and provide recommendations to prevent future occurrences. The board members represented Federal and State governments and private industry.
Based on the reports submitted by the investigators, the board concluded that the failure probably ocurred because the shoring tower assemblies were not constructed in accordance with the falsework plans approved by the Federal Lands Division, [1](1) The board went on to recommend that, to prevent such occurrences in the future, falsework specifications should be revised to better define the responsibilities of material suppliers, contractors, and engineers.
This recommendation was signed into law by the Department of Transportation and Related Agencies Appropriations Bill of Fiscal Year 1991, which states in part that ". . . the Committee on Appropriations directs the Federal Highway Administration to undertake the research project recommended in the report entitled |Investigation of Construction Failure Maryland Route No. 198 Bridge Over the Baltimore-Washington Parkway'" [2]
The bill goes on to specify that the research project should produce approved guidelines, improved specifications, and a falsework construction handbook. The guidelines and specifications should apply both to construction projects under direct FHWA supervision and those carried out by the States with Federal-aid highway funds. [2]
Given the complexity of the work involved in developing a specification, the Committee has set a final due date of December 1992 for the research program's report. This article describes recent falsework failures since the Baltimore-Washington Parkway incident which emphasize the even greater need for better guidelines on bridge temporary works and progress to date in fulfilling the Committee's research program mandate.
Recent Falsework Failures
Several other collapses have occurred since the Baltimore-Washington incident. These recent failures have motivated the task group in their mission. They are described below:
* On April 24, 1990, falsework for the Lake
Street-Marshall Avenue bridge near St. Paul, Minnesota,
collapsed, killing one worker (figure 2). An
estimated 300 tons (272 Mg) of steel and 1,100 (998 Mg)
tons of concrete fell into the Mississippi River.
According to the State bridge engineer, the failure
was related to human design error. [3] * On June 18, 1990, the falsework supporting one
section of a 63-ft (19.15-m) welded plate tub girder
being erected at N 370 and U.S. 75 in Bellevue,
Nebraska, collapsed, dropping the girder. There
were no injuries. Investigation and analysis showed
that the collapse was initiated by lateral loads on the
false work caused by strong southwest winds. The
failure of the falsework was progressive, ending
with the collapse of the girder. [4] * On July 13, 1990, the U.S. 45 bridge under
construction over Spring Brook in Antigo, Wisconsin,
collapsed as placement of deck concrete was nearing
completion. The cause of the collapse is believed to
be shear failure of the 48 bolts connecting the deck
form supports to substructure abutment walls. This
initial failure led to subsequent shear failure of all
but one of the remaining bolts. [5] * On October 10, 1990, a section of the superstructure
falsework for an elevated connector ramp of the
I 880/SR 238 interchange in San Leandro, California,
collapsed (figures 3 and 4). Three workers were
injured but there were no fatalities. The accident
occurred during the erection of a falsework beam
over an existing ramp. The cause of the collapse is
being investigated by the California Department of
Transportation and the California Department of
Occupational Safety and Health. [6]
In March 1990, the FHWA established a multidisciplinary Scaffolding, Shoring, and Forming Task Group to develop and guide the mandated falsework research program. The task group includes representatives from the FHWA, the American Association of State Highway and Transportation Officials (AASHTO), the Associated General Contractors, the American Road and Transportation Builders Association, the Transportation Research Board, and the Scaffolding, Shoring, and forming Institute.
The first meeting of the task group was held on April 17, 1990. During this meeting the task group identified the following as priority activities:
* Survey existing specifications on bridge temporary
works, synthesize them, and identify any gaps. * Establish a standard construction specification
Most Recent Business Articles
- Your feedback
- Why fly solo when an executive assistant can accelerate your CLNC® business?
- The CLNC® mentors held the key to my first case and to my CLNC® success
- Atlanta CLNC® 6-day certification seminar photo galleryplus sign up today for spring 2009 to save $100.00
- Announcing the 2009 NACLNC® conference keynote speaker, Stedman Graham: move like a maverick for breakaway CLNC® success at the 2009 NACLNC® conference
Most Recent Business Publications
Most Popular Business Articles
- Using object-oriented analysis and design over traditional structured analysis and design
- Big Fish Games Migrates Upstream to Fisher Plaza; High Growth Online Gaming Firm Vaults Fisher Plaza Occupancy Rate Above 90%
- Top of the line: some of the world's most well-respected doctors practice in South Florida. A guide to choosing the best physician specialists - Top Doctors in South Florida
- Sand filter basics: high-rate sand filters can be confusing for those new to the business. Understanding valve modes is the key
- BEHR Paints Introduces a Colorful New Way to Paint and Prime All in One with BEHR Premium Plus Ultra™ Interior

