Featured White Papers
- 9 critical reasons to automate performance management (SuccessFactors, Inc.)
- Enterprise PBX buyer's guide (VoIP-News)
- Enterprise PBX comparison guide (VoIP-News)
The latest A-12 wranglings: Honey, this letter from the collection agency says we owe $2.3 Billion
Army Lawyer, Jan-Feb, 2003
The Latest A-12 Wranglings: Honey, This Letter from the Collection Agency Says We Owe $2.3 Billion
Last year's Year in Review (1) reported that the Court of Federal Claims (COFC), on remand from the Court of Appeals for the Federal Circuit (CAFC), dismissed the plaintiffs' complaint in the longstanding, multi-billion dollar A-12 litigation, McDonnell Douglas Corp. v. United States. (2) hat decision, rendered on 31 August 2001, apparently left the Boeing Corp. (the successor to McDonnell Douglas) and General Dynamics Corp. billions of dollars in debt to the Navy. (3) Although the plaintiffs appealed that decision to the CAFC, (4) the parties spent most of the year in settlement talks. (5)
On 30 August 2002, the Navy Comptroller, Dionel M. Aviles, demanded that General Dynamics and Boeing pay the Navy $2.3 billion dollars, or the Navy would "refer the matter to the Defense Finance and Accounting Service for collection." (6) In response, General Dynamics called the letter "an unseemly negotiating tactic, and an apparent effort to gain advantage during settlement talks." (7) According to the Navy, the contractors owe a little over $1.3 billion in principal and $1 billion in interest. As of 30 September 2002, $191,804 in interest accrued each day. The letter concluded on a somewhat conciliatory note, stating that the Navy "fully support[s]" settlement discussions. (8)
Re-establishing a Delivery Schedule After Government Waiver: There's a Right Way and A Wrong Way
Generally, the government has the right to terminate a contract immediately upon a contractor's failure to deliver or perform on time. (9) When the government disregards the delivery schedule and encourages or condones continued performance, however, it waives the right to terminate, unless it re-establishes a delivery or performance schedule. (10) The government can reimpose the schedule either bilaterally or unilaterally. (11) Three boards of contract appeals recently considered variations on this scenario of failure to perform, waiver, and attempted reestablishment. (12)
In Beta Engineering, Inc. (13) the Defense Supply Center Philadelphia (DSCP) contracted with Beta Engineering, Inc. (Beta Engineering) to supply lock-release levers (14) for aircraft machine guns. (15) The contract required Beta Engineering to deliver first-article test samples (FATS) on a specified date. (16) A clause in the contract provided that if the contractor failed to deliver any FATS on time, "the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause." (17) The levers had to pass a detailed preliminary inspection before first article testing. (18)
Although Beta Engineering failed to meet the FATS submission deadline, 30 April 2001, the government procurement contracting officer (PCO) did not terminate the contract or notify Beta Engineering that it was delinquent. (19) After 30 April 2001, the PCO even authorized the contractor to use a different grade of steel and allowed the contractor to conduct a preliminary inspection. The Armed Services Board of Contract Appeals (ASBCA) found that these government acts and failures to act "disestablished 30 April 2001 as the deadline for submission of FATS." (20) On 17 May 2001, the contractor, with a government representative present, conducted a preliminary inspection. The inspection was not completed successfully. After the failed inspection, the contractor proposed a new date for a second FATS preliminary inspection. The PCO, however, took no action to reestablish a new FATS due date and failed to respond to the contractor's offer to submit new FATS, leaving Beta Engineering "in limbo." (21) The PCO terminated the contract on 15 August 2001. (22)
Citing an earlier decision, the board stated, "[w]e have held that a termination for default for failure to deliver a first article was improper where 'there was no enforceable first article delivery schedule in place at the time the government terminated the contract for default." (23) The board found that after Beta Engineering missed the FATS deadline, not only did the government fail to terminate the contract, but the government encouraged further performance by approving the lower-grade steel and by proceeding with preliminary inspections. The government thereby waived the FATS delivery due date. By leaving Beta Engineering in limbo about whether and when it could submit a second set of FATS, the government left itself "without an enforceable FATS delivery schedule." (24) The government, therefore, improperly terminated the contract for default. (25)
In Rowe, Inc., (26) the General Services Administration (GSA) also faced missed delivery dates. After allowing the contractor, Rowe, to miss two delivery dates, however, the GSA contracting officer (CO) properly set a new deadline. When Rowe missed the new delivery date, the government was in a position to properly terminate the contract for default. (27)