Aurizon Mines Ltd.: Additional Encouraging Results from Defintion Drilling at Casa Berardi-On Schedule for November Start Up
Market Wire, September, 2006
Aurizon Mines Ltd. (TSX: ARZ)(AMEX: AZK) is pleased to present additional results from the ongoing definition drilling on Zone 113 and a progress report on development activities at its 100 percent owned Casa Berardi Gold Project located in north-western Quebec, Canada.
"The completion of definition drilling of Zone 113, along two additional levels, confirms that the initial gold production from Casa Berardi should exceed that outlined in the current mine plan." said David Hall, President and CEO of Aurizon. "Casa Berardi remains on schedule and on budget to commence gold production in approximately 10 weeks' time, despite unscheduled interruptions and distractions. We anticipate that Aurizon shareholders will benefit not only from strong gold prices, but also from higher initial gold production. Aurizon is poised to realize the re-rating associated with producing companies."
Five underground rigs (two for exploration and three for definition) and two surface exploration rigs are currently active on site. Additional drill results are expected shortly.
Definition drill program on Zone 113 between 650-720 metre levels
Additional definition drilling performed between the 650 and 720 metre levels covered the area where the initial stope development will occur. Fifty (50) infill and definition holes have previously been reported within this area and fifty seven (57) additional definition holes have now been completed from the 670 (1 hole), 690 (34 holes) and 710 (22 holes) metre levels. Best results are as follows.
--------------------------------------------------------------------
--------------------------------------------------------------------
Gold Gold Gold Gold
Ounces Grams Ounces Grams
Definition per per Thickness Definition per per Thickness
Hole # ton tonne (metres) Hole # ton tonne (metres)
--------------------------------------------------------------------
690-10 0.31 10.7 7.7 710-01 0.89 30.7 2.9
--------------------------------------------------------------------
690-13 0.62 21.4 9.0 710-07 0.60 20.8 6.5
--------------------------------------------------------------------
690-21 0.46 15.7 7.5 710-09 0.46 15.7 15.1
--------------------------------------------------------------------
690-22 0.37 12.7 26.0 710-10 0.99 34.0 12.4
--------------------------------------------------------------------
690-24 0.34 11.5 7.5 710-11 0.97 33.4 14.5
--------------------------------------------------------------------
690-25 0.29 10.1 12.1 710-12 0.69 23.7 4.2
--------------------------------------------------------------------
690-26 0.46 15.9 16.5 710-13 0.25 8.7 17.5
--------------------------------------------------------------------
690-28 0.19 6.5 21.3 710-18 0.62 21.4 21.0
--------------------------------------------------------------------
690-29 1.51 52.1 2.3
--------------------------------------------------------------------
690-31 0.28 9.7 22.2
--------------------------------------------------------------------
690-32 0.22 7.7 12.5
--------------------------------------------------------------------
690-33 0.20 6.8 21.0
--------------------------------------------------------------------
--------------------------------------------------------------------
Missing numbers in the sequence are shown on the sketch attached to this press release, which shows all holes drilled in this area of Zone 113.
A high grade core of Zone 113 plunges steeply to the east as shown on the sketch. An updated mineral reserve estimate should be completed during the fourth quarter, 2006.
Information from the definition drilling is being used to outline the precise ore stope dimensions. Footwall drifts, which are set 20 metres apart, are being used as the collar locations of the current drill program.
Progress Report on Casa Berardi Development
- Start up of commercial production remains on target for early November 2006.
- Over 400 people are currently active on site.
- Shaft sinking: Completed and has reached the shaft bottom at the 760 metre elevation. Related underground infrastructure is anticipated be completed early in the fourth quarter 2006. Shaft access has been completed on the 280, 550 and 690 metre levels.
- Ramp access: Completed and has reached the 730 metre level, which is the depth required for initial production.
- Drift access development: Completed on four of the five required access drifts, and the fifth access drift, on the 730 metre level, is substantially complete. Construction of draw points is underway on the 650, 670 and 690 metre levels, and will be initiated on the 710 and 730 metre levels by the end of this month.
- Construction of a rockfill network: In progress. Modification to the existing cement plant and construction of the rockfill dump station should be completed this quarter. Underground drilling of the slurry distribution holes and development of the fill raises are currently underway from the 690 metre level to the surface. In addition, the fill raise collar has been completed ahead of schedule.
- 5 Rules for Immediate Annuities
- Death in the Family: 12 Things to Do Now
- Dumbest Things You Do With Your Money
- 6 Online Networking Mistakes to Avoid
- 401(k) Mistakes to Avoid
- 5 Economic Scenarios to Keep You Up at Night
- The Real ‘Best Places to Retire’
- Best Credit Cards for You
- 12 Tough Questions to Ask Your Parents
- The Real ‘Best Colleges’
- Home Buyer Tax Credit: How to Cash In
- Why You Shouldn't Bash Cash
- 8 Phony 'Bargains' and Better Alternatives
- Danger: 3 Debit Card Scams to Avoid
- 6 Myths About Gas Mileage
- 29 Fees We Hate Most
- Quick and Easy Ways to Boost Returns
- Best Stocks to Buy Now
- Lower Your Taxes: 10 Moves to Make Now
- New Jobs: 8 Lessons from Real-Life Career Switchers
- The New Job Market: Who Wins and Who Loses?
- Health Care Reform's Public Option: Everything You Need to Know
- Volunteer Work When Unemployed: Should You Work for Free?
- Whose Recovery Is This?
- Long-Term-Care Insurance: 4 Biggest Risks to Avoid
Content provided in partnership with
Most Recent Business Articles
- "Do not rely on a single economy" ; Larsen and Toubro (L and T) was affected due to the slowdown particularly the products businesses, which include switchgears, construction equipment and industrial bars.
- "The first deliberate call we took was not to lay off anybody" ; The diversified group decided to reskill all surplus workers.
- "Government had to step up its demand" ; The downturn affected the government as much as India Inc. The outgoing advisor to the Government of India details its impact and its lessons.
- "Help your customers even in difficult times" ; Oil was at an all-time high at over $135 per barrel just before the financial meltdown. Then oil crashed to a low of $35 per barrel in January this year, bringing down any fresh demand for pipes fr
- "You have to be visible as a leader" ; Transparency is a standard operating procedure for communications during a downturn.
Most Recent Business Publications
Most Popular Business Articles
- 7 tips for effective listening: productive listening does not occur naturally. It requires hard work and practice - Back To Basics - effective listening is a crucial skill for internal auditors
- Using object-oriented analysis and design over traditional structured analysis and design
- FAS 109: a primer for non-accountants - Financial Accounting Standards Board's "Statement 109: Accounting for Income Taxes"
- LIFO vs. FIFO: a return to the basics
- Design a commission plan that drives sales - Sales Commissions